BE RU EN

Battery Plant In Brest Is Put On Hold

  • 12.06.2019, 15:25

The Brest protests are bearing fruit.

The battery factory under Brest is still undergoing the acceptance procedure. The work of the commission was extended until June 21, the company informed tut.by.

On June 11, the plant's management met with journalists. Company director Siarhei Melniakovich said that all commissioning works were completed on April 10, Viacherni Brest reports.

According to him, there are two ways to comply with the accepted standard - to reduce emissions to the design standard (i.e., up to 3 kg per year) by "working with technological equipment," or to introduce changes in the project, which is also possible, but may take a little longer. So far, the management has decided to follow the first path.

We remind that the opponents of the battery launch are trying to achieve the complete closure of the harmful enterprise.